![]() ![]() And add a new field (such as Activity1) to replace the system Activity field. Such as if you are using Agile system process, you can create an inherited process (myagile) from Agile, then change your team project to the inherited process. The workaround is create an inherited prcess and a new field to replace the system Activity field. ![]() For VSTS, you can not change system fields (such as Activity) in System processes (Agile, Scrum and CMMI).